Comcast Generator Upgrade – San Jose


Project Media:


Project Manager:

Image loading Phil Strawn

Supertintendent:

Kevin Simon

Project Details:

Project Name:

Comcast Generator Upgrade – San Jose


Location:

San Jose, CA


Owner:

Comcast Corp. (Comm/Net Systems, Inc.)


Architect:

Third Shoe, Inc.


Project Duration:

9/15/16 - 1/31/17

Project Description:

Modern Building Company began construction at the San Jose Comcast site on September 15th, 2016 with a firm deadline of January 31st, 2017. The general scope of work includes converting the existing loading dock into a generator service yard for new emergency power service to critical infrastructure fiber distribution center.

All concrete work will be self-performed by Modern Building Company crews. This project location is a power distribution upgrade to the west coast hub for Comcast. At no time can the site go down or off-line.

This is Modern’s fourth project for this client.

 

16061- 10.28.16

Update: 10.28.16